5. Installation of the setting-up kit
5.7.3
Connecting the clear water extraction
The outlet of the clear water lifter is routed into the 90° bend or into the internal sampler.
5.8
Installing the feed lifter in the preliminary cleaning system
The two vertical pipes of the feed lifter are stabilised directly under the middle socket connector using two
PVC pipe clamps and clips.
The third PVC pipe clamp is prepared for tank installation using the stainless steel bracket supplied (see
top right-hand image). This is then installed in the tank on the half-open DN 100 bottom outlet.
The lower bend of the feed lifter is then placed in this PVC pipe clamp and can be additionally secured
using M3x16 Spax screws.
The feed lifter outlet is pushed into the 100 mm pipe to the SBR basin. These pipe connections are also
secured using M3x16 Spax screws.