a
SSembly
11. Insert round end of tube assembly into the open hole
on the bagger housing and push it in approximately
8-10".
12. Lift the mower discharge chute and guide the end of
the tube down onto the opening. Keep the top tube end
inserted into the bagger housing. Ensure that the top
lip of the tube chute is on top of the mower deck and
the bottom lip is under the support bar. With the bottom
chute correctly in place, attach the chute hooks into the
holes near the deck wheels as shown.
Lift Discharge Chute
10
D142100 R1 Bagger Manual_Final - English.indd 10
13. A correctly installed tube assembly will look as shown
below. At this point, TIGHTEN THE (4) BOLTS FROM
STEP 3 SECURELY.
14. Locate the (3) Grass Bags and slide them onto the
main frame.
15. Close lid and secure it with the (2) lid straps as shown.
RAVEN B463 Bagger System
4/9/2015 8:51:33 AM