6
FIXATION AFTER CONNECTION PIPES
1. After connection to pipes, fix the PMV Kit using the attached binding band so that it is held
closely to the gas pipe.
Binding band L
Binding band M
Binding band M
Heat insulating pipe
Refrigerant pipe
(Liquid side)
2. To avoid propagation of sound or vibration, wrap cushion material around the liquid pipes of
PMV Kit, and then set with the hanging bolts within 1m intervals.
Also, when mounting PMV Kit on the wall, put the cushion material between PMV Kit and the
wall to avoid propagation of sound and vibration.
Hanging bolt
Insulator or
cushion material
(Locally procured)
Note
• Install PMV Kit as illustrated within 15 degree vertically and horizontally, respectively.
EN-11
Binding band M
Binding band L
Binding band M
Refrigerant pipe
(Gas side)
Heat insulating pipe
Refrigerant pipe
(Liquid side)
1 m or less
Hanging bolt
Refrigerant pipe
Insulator or
cushion material
(Locally procured)
PMV Kit
7
ELECTRIC WORK
1. Using the specified wires, ensure to connect the wires, and fix wires securely so that the
external strength of the wires do not transmit to the connecting part of the terminals.
Incomplete connection or fixation may cause fire, etc.
2. For electric work, strictly follow to the Local Regulation in each country and the Installation
Manual, and use an exclusive circuit.
Capacity shortage of power circuit or incomplete installation may an electric shock or fire.
REQUIREMENT
• Perform the electric wiring so that it does not come to contact with the high-temperature part of the pipe.
The coating may melt resulted in an accident.
• After connecting wires to the terminal blocks, provide a trap and fix wires with the wire clamp.
• Store the refrigerant piping line and control wiring line in the same line.
• Do not turn on the power of the indoor unit until vacuuming of the refrigerant pipes completes.
7
WARNING
EN
EN-12