TRIPLE INSTALL WITH 30" BF IN CENTER POSITION - 24" COLUMNS
NOTE: These instructions do not replace individual product installation instructions. Refer to
product installation instructions for full installation process.
Doors Open Independently
1. Panel required between units: ¾"
thick and 1 1/2" thick minimum, 3.5-6"
deep.
2. Position of ZIF241 & ZIR241 can be
interchanged
3. Heater kits required: ZUG30 installed
on left side of ZIK30 & ZKUN installed
on left side of ZIR/ZIF241.
4. Ensure panel weight does not exceed
maximum rating.
5. When installing custom handles,
ensure handle position allows full door
opening of adjacent units.
6. Center unit requires 90° hinge pin.
7. Each unit needs its own anti tip
system installed per individual
installation instructions.
8. Electrical and water locations for
each product are per individual install
instructions.
9. Mounting template should be adjusted
by 7/8" from the handle side of the
door.
4
Heater Kit
ZUG30
24" FZR CLM
30" CONVERTIBLE
ZIF241NPNII
CABINET PANEL
CABINET PANEL
3/4"
23-13/16"
24-9/16" column +
3/4" panel opening
Total opening width: 79-7/8"
Door Panel Width:
24-7/16"
Heater Kit
24" REFRIG CLM
ZIK30GNNII
CABINET PANEL
25-5/16" column +
30" ZIK opening
Door Panel Width:
29-3/4"
NOTE: For independent door
opening, door panel cannot
cover 1-1/2" spacer panel.
ZKUN
ZIR241NPNII
1-1/2"
23-13/16"
panel opening
Door Panel Width:
23-9/16"