ENG
Procedure
1.
Lift the properly secured cooling unit slowly and evenly, see figure Fig. 16.
2.
Mount the cooling unit horizontally.
•
Permissible inclination up to 0.5° from the horizontal plane (switch cabinet + cooling unit).
3.
Set down the cooling unit on the surface seal (2) on the switch cabinet roof and align it with the cut-outs.
4.
Make sure that the condensate drain (3) is at the lowest point. Lay the condensate drain hose continuously with a
gradient and without any kinks.
–
The condensate drain hose must not exceed 3 m in length.
–
Regularly check during operation as to whether the condensation drains off properly.
5.
Position the cooling unit precisely in the cut-out.
6.
Fasten all six locking levers (4) on the inside of the switch cabinet, see Fig. 16 - Detail cut-out "A".
7.
Turn all six locking levers (4) on the inside of the switch cabinet over the rail to fix the cooling unit, see Fig. 16 - Detail
cut-out "B".
The cooling unit is mounted on the switch cabinet and ready for electrical connection, see "Electrical connection",
Page 41.
Operating Manual | Roof-mounted Cooling Unit | Multi Controller (MC) – 400 / 460 V, 3~ | 086100033c
36/37