Produktgruppen 522, 592
8 von 30
Abbreviation
UM
B
Table 1: Abbreviation legend
Close the gas stopcock if applicable.
Disconnect the machine from the electric mains supply provided in accordance with all relevant regulations and the gas supply
(if applicable), and ensure utilities cannot be switched on again in error.
Place the plinth in position and mark the hole positions, see Fig. 2, Pos. 1.
Note
Take care to comply with the minimum spacings given in the installation plan.
The gap between the machine and a wall at the side must be at least 10 mm.
Drill 4 holes 12 mm Ø approx. 65 mm deep in the floor as shown, Fig. 3.
Insert 4 S12 Rawl plugs flush in the holes, Fig. 4, Pos. 1.
Fit spacer plates, Fig. 4, Pos. 2, as appropriate and use the spirit level to level the plinth.
Secure the plinth with four 8 x 65 hexagon head wood screws, Fig. 4, Pos. 3, 8.4 washers, Fig. 4, Pos. 4, and 38 mm Ø washers,
Fig. 4, Pos. 5, to the floor.
Place the machine on the plinth.
Danger!
Risk of injury, particularly to the back. The relation of the weight of the machine to the physical strength of the technician must be taken
into account. For machine weight details, see the appropriate operating instructions.
Risk of crushing. When carrying out work, ensure that parts of the body, especially the hands and feet are not positioned under or
between machines.
Fit 4 clamps, Fig. 5, Pos. 1, over the machine feet.
Insert four M6 bolts, Fig. 5, Pos. 2, with B6.4 galvanised washers, Fig. 5, Pos. 3, from above through the existing holes.
Secure the 4 clamps from below with 38 mm Ø washers, Fig. 5, Pos. 4, B6.4 galvanised washers, Fig. 5, Pos. 3, and M6 nuts,
Fig. 5, Pos. 5, tightened from below.
Danger!
Risk of toppling and falling! It is absolutely essential to secure the plinth to the floor and the machine to the plinth.
Note
Match the height of the vent duct.
Note
Fixing materials for a floating screed floor are to be provided on site.
Plinth UG 8250 / UG 8330
Fit the 4 rubber bumpers in the plinth sides, Fig. 6, Pos. 1.
Fit the 2 side panels in the slots in the dryer base plate, Fig. 6, Pos. 2, and secure them with the raised-head screws 4.8 x 9.5,
Fig. 6, Pos. 3.
Fit the front panel Fig. 6, Pos. 4, and secure it with the raised-head screws 4.8 x 9.5, Fig. 6, Pos. 5.
Carry out appropriate safety checks.
Reconnect the machine to the electric mains supply provided in accordance with all relevant regulations, and the gas supply
(if applicable).
en
28.09.2010
Diese Unterlagen dürfen ohne unsere Genehmigung weder vervielfältigt noch Dritten zugänglich gemacht werden. Eigentumsrechte vorbehalten.
Explanation
Miele plinth
Floor fastening
Umbau- und Montageanweisung
M.-Nr. 07946040

Publicidad

loading

Este manual también es adecuado para:

Uo 8330Ug 8250Ug 8330