The Automatic Commissioning consists of several steps:
1.
Push the start button to start the commissioning
procedure.
Select the preferred language, refer to Select the
2.
preferred language.
3.
Set the actual time and date, refer to Set the actual
time and date.
4.
Select the correct system fluid, refer to Select the
correct system fluid.
5.
Set the pressure levels, refer to Set the pressure
levels.
6.
Fill up the unit with system fluid, refer to Fill up the
unit with system fluid.
7.
Execute the functional test, refer to Execute the
functional test.
Select the preferred language
1.
Select your preferred language. The indicator shows
the selected language.
2.
Select the next page button ( > ).
Set the actual time and date
1.
Set the actual time. Move the wheels of the time
indicator (HH:MM:SS) to the correct time in hours
(HH), minutes (MM), and seconds (SS).
2.
Set the correct time zone (UTC). Move the wheel to
the correct time zone.
3.
Select the next page button ( > ).
4.
Set the actual date. Move the wheels of the date
indicator (DD:MM:YY) to the correct date in day
(DD), month (MM), and year (YY).
5.
Select the next page button ( > ).
Select the correct system fluid
1.
Select the type of fluid in the system. The indicator
shows the selected type.
2.
Select the next page button ( > ).
Fill up the unit with system fluid
1.
Open the valves. Refer to § 5.4.1.
2.
Select the next page button ( > ).
3.
Deaerate the pump. Refer to § 5.4.1.
4.
Select the next page button ( > ).
13
Set the pressure levels
A
C
1.
Drag the label of the maximum pressure (A) to the
desired maximum pressure.
2.
For units of -R and -B versions: Drag the label of
the operating pressure (B) to the desired operating
pressure.
For units of -R and -B versions: Drag the label of
3.
the refill pressure (C) to the desired refill pressure.
NOTE
The minimum operating pressure (D) cannot
be changed.
4.
Select the next page button ( > ).
Execute the functional test
1.
Push the start button to start the functional test.
The functional test only starts if the unit
meets the following conditions:
The deaeration tank is filled with
•
system fluid.
The measured pressure is above the
•
minimum pressure (0.8 bar).
For -B versions: the break tank is
•
filled with refill fluid.
English
B
D
User manual - 1.0