5.9
Installing the holding plate in the SBR basin
5.9.1
Inserting the holding plate
The ventilation, including the concrete weight, is inserted into the tank. The complete holding plate as-
sembly is pushed onto the ventilation downpipe and fitted onto the crossbar. The holding plate is fitted on
the inflow side.
The stainless-steel hose connector with thread is then screwed on to the ventilation downpipe - make sure
to use a Teflon seal.
5.10 Connecting the clear water extraction
The outlet of the clear water lifter is routed into the 90° bend or into the internal sampler.
Connecting clear water lifting without sampler
5.10.1 Connecting the excess sludge lifter
An HT pipe (DN 110, L = 150 mm) is pushed from
the inside to the outside through the seal at the
opening (see Section 4.3) for the sludge return.
5. Installation of the setting-up kit
53 / 144
Connecting clear water lifting with sampler
The sludge return line is slid into the socket of the
fitted HT pipe.