Graf KLARO Easy Instrucciones Para El Montaje página 55

Sistema de depuración
Ocultar thumbs Ver también para KLARO Easy:
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

5.11 Installing the feed lifter in the preliminary cleaning system
The two vertical pipes of the feed lifter are connected directly under the middle socket connector using
two PVC pipe clamps and clips.
The third PVC pipe clamp is prepared for tank installation using the clamp supplied (see top right-hand
image). This is then clamped onto the floor rib. Ensure that the clamp is flush on the rib and is not sitting
on a small cross strut.
The lower bend of the feed lifter is then placed in this PVC pipe clamp and can be additionally secured
using M3x16 Spax screws.
The feed lifter outlet is pushed into the 100 mm pipe to the SBR basin. These pipe connections are also
secured using M3x16 Spax screws.
5. Installation of the setting-up kit
Carat 4800/6500 position 1/4
Carat 2700/3750 position 1/3
54 / 144

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

Klaro eKlaro l

Tabla de contenido