Eaton Powerware 5125 Guia De Instalacion página 13

Ocultar thumbs Ver también para Powerware 5125:
Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

To install the EBM in a rack:
1.
Place the EBM on a flat, stable surface with the front of the EBM
facing toward you.
2.
Attach the supplied mounting handles to the mounting brackets and
secure with the supplied screws (see Figure 1).
3.
If installing additional EBMs, repeat Steps 1 and 2 for each cabinet.
NOTE The UPS and EBMs MUST be installed at the bottom of the rack. If placed in a rack
with existing equipment, the rack must be reconfigured to allow the UPS installation at the
bottom of the rack.
NOTE The EBMs must be installed below the UPS as shown in Figure 2.
4.
Slide the EBMs into the rack.
5.
Secure the units to the rack according to the rail kit instructions.
EATON Powerware
®
5125 (9910-P33) EBM Installation Guide for IBM
Mounting Handle
Figure 1. Installing the Mounting Handles
UPS
Optional
EBMs
Figure 2. Rack-Mount UPS with EBMs
®
Applications
INSTALLATION
Mounting
Bracket
S
3
164201358 Rev C

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

9910-p33

Tabla de contenido