Installing a Power Distribution
System
Installing a power distribution system in a Sun Rack consists of three steps:
"Installing Cable Harnesses" on page 1-1
I
"Installing Power Strips" on page 1-6
I
"Installing Power Sequencers" on page 1-7
I
Additionally, once systems are installed in the rack, you may label the system power
cords with the labels provided.
Installing Cable Harnesses
Each cable harness consists of three cables bundled together on a carrier plate.
Viewed from the back of the rack, the cable harnesses and power sequencers are
mounted on the left side of the rack. The lower cable harness (B) is shorter than the
upper harness (A). Each cable carrier plate is installed in the slot above its respective
sequencer. It is more convenient to install the cables for the lower sequencer (B) first.