4.5.4.2. Discharge profile.
Fig. 25. Discharge mode.
Battery charge
Mains
-
Battery
-
PV
-
Fig. 26. Work priorities in Discharge mode.
When the discharge profile is enabled, the battery has the option
of discharging when necessary. The installation's consumption
will be supplied first with the solar panel power, and if this is not
enough, the battery will be discharged to supply the consumption.
If there is still a lack of power, the grid will be used. In no case will
the battery be charged with the discharge profile enabled, nor with
the solar panel surpluses.
4.5.4.3. PV priority charge profile.
Fig. 27. PV priority Charge mode.
Battery charge
Mains
-
PV surpluses
-
PV
1
Fig. 28. Work priorities in PV priority Charge profile.
In the PV priority charge profile, the battery is charged from the
solar panel power; if this is sufficient and therefore there are
surpluses, they will be directed to the installation's consumption,
if there is any. If the surpluses are not enough for the installation's
consumption, the grid is used.
USER MANUAL
Prioritisation
Supplying the loads
3
2
1
Prioritisation
Supplying the loads
2
1
-
4.5.4.4. PV + Grid Charge profile.
Fig. 29. PV priority charge profile.
Battery charge
Mains
2
PV surpluses
-
PV
1
Fig. 30. Work priorities in PV priority Charge profile.
In this charge profile, the battery is first supplied by the solar panel
power and, if this is not enough, the missing power is imported
from the grid. If the solar panel power is sufficient and therefore
there are surpluses, these are directed to supply the installation's
consumption. In the event that consumption is higher than the sur-
pluses, the grid will be used.
4.5.4.5. Standby profile.
Fig. 31. Standby profile mode.
Battery charge
Mains
-
PV
-
Fig. 32. Work priorities in Standby profile.
The standby profile is enabled by default when there is no profile
enabled at that time. In this mode, the hybrid acts as an On-Grid
inverter without battery, as the battery is virtually disconnected
and not used. Therefore, the installation's consumption is supplied
first by the solar panel power and then by the grid.
Prioritisation
Supplying the loads
2
1
-
Prioritisation
Supplying the loads
2
1