6 Commissioning [specialist]
1. After the low-loss header is installed, put the heating circuits onto the low-loss header
and firmly tighten the thread connections.
2. Connect the distribution manifold to the boiler (do not forget the sealings).
3. Check all screw connections and tighten them if necessary.
4. Carry out the pressure test.
5. Mount the insulation of the low-loss header
6.1
Accessories: compression fitting (not included in delivery)
The connection to the heating installation can be carried out fast, pressure-proof and without
soldering when you use the optionally available compression fittings.
Not included in the
scope of delivery!
2017/01
1. Push the union nut ② and the cutting ring ③ onto the
copper pipe ①. The pipe must protrude at least 3 mm
from the cutting ring in order to ensure the force
transmission and the sealing.
2. Insert the support sleeve ④ into the copper pipe.
3. Insert the copper pipe with the plugged-on individual
parts (②, ③ and ④) all the way into the housing of
the compression fitting ⑤.
4. First screw the union nut ② manually.
5. Tighten the union nut ② by rotating one full turn.
Secure the housing of the compression fitting ⑤
against distort in order to avoid damaging the
sealing ring.