Protection Against Contamination When Installing Pipes; Example Of Connection - Daikin CMSQ200A7W1B Manual De Instalación

Ocultar thumbs Ver también para CMSQ200A7W1B:
Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 96
Processing the gas side accessory pipe (2)
Only in case of connecting at lateral side, cut the gas side
accessory pipe (2) as shown in figure 12.
1
Gas side accessory pipe
2
Cutting location
3
Gas side piping (field supply)
4
Base
Unit type
A
CMSQ200
166
(mm)
CMSQ250
156
(mm)
NOTE
When connecting the piping on site, be sure to
use the accessory piping.
Make sure the onsite piping does not come into
contact with other piping, the bottom frame or side
panels of the unit.
4
Branching the refrigerant piping
For installation of the refrigerant branching kit, refer to the
installation manual delivered with the kit.
(See figure 14)
1
Horizontal surface
Follow the conditions listed below:
- Mount the refnet joint so that it branches either
horizontally or vertically.
- Mount the refnet header so that it branches horizontally.
Installation of the multi connection piping kit
(See figure 18)
- Install the joints horizontally, so that the caution label (1)
attached to the joint comes to the top.
Do not tilt the joint more than 15° (see view A).
Do not install the joint vertically (see view B).
- Make sure that the total length of the piping connected to
the joint is absolute straight for more than 500 mm. Only
if a straight field piping of more than 120 mm is
connected, more than 500 mm of straight section can be
ensured.
- Improper installation may lead to malfunction of the
outdoor unit.
5
Piping length restrictions
Make sure to perform the piping installation within the range of
the maximum allowable pipe length, allowable level difference
and
allowable
length
after
"6.6. Example of connection" on page 7.
Installation manual
6
B
C
D
16
199
246
17
188
247
branching
as
indicated
in
6.5.
Protection against contamination when
installing pipes
-
Take measures to prevent foreign materials like moisture and
contamination from mixing into the system.
Installation period
More than a month
Less than a month
Regardless of the period
-
Great caution is needed when passing copper tubes through
walls.
-
Block all gaps in the holes for passing out piping and wiring
using sealing material (field supply). (The capacity of the unit
will drop and small animals may enter the machine.)
Example: passing piping out through the front
1
2
3
1
2
3
After all the piping has been connected, make sure there is
no gas leak. Use nitrogen to perform a gas leak check.
Protection method
Pinch the pipe
Pinch or tape the pipe
Plug the areas marked with "
".
(When the piping is routed from the
front panel.)
Gas side piping
Liquid side piping
CMSQ200+250A7W1B
Air conditioning system
4PW47543-1

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

Cmsq250a7w1b

Tabla de contenido