Electrical Connections; Important Advice - Ecoflam BLU 500 P Manual De Instrucciones

Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

B LB 447 Blu 500 ÷ 700 P
Once connected the burner to the gas pipeline, it is necessary to control that this last is perfectly sealed. Also verify that
the chimney is not obstructed. Open the gas cock and carefully bleed the piping through the pressure gauge connector,
then check the pressure value trough a suitable gauge. Power on the system and adjust the thermostats to the desired
temperature. When thermostats close, the sealing control device runs a seal test of valves; at the end of the test the bur-
ner will be enabled to run the start-up sequence.
All burners factory tested at 400 V 50 Hz three-phase for motors and 230 V 50 Hz monophase with neutral for auxi-
liary equipment. If mains supply is 230 V 50 Hz threephase withuot neutral, change position of connectors on burner
as in fig. Protect burner supply line with safety fuses and any other devices required by safety standards obtaining in the
country in question.
PRELIMINARY CHECKS
Before starting up the boiler check the following:
• gas type and feed pressure;
• gas valves closed;
• the seals in the pipe fittings;
• gas pipe breather and input pressure;
• that the cable complies with the diagram and the phase and neutral wires correspond;
• that the burner shuts down when the boiler thermostat opens
• the seal of the boiler furnace which prevents air from entering
• the seal on the flue-boiler pipe fitting;
• the condition of the flue (sealed, free from blockage, etc.).
If all these conditions are present, start the burner. The control device starts the motor to carry out prewashing of the
combustion chamber. During this prewash period (about 30 seconds) the device checks that air pressure is correct via
the air pressure switch. At the end, it supplies power to the transformer and opens the gas valves. The flame must be lit
and stabilize within 3 seconds, which is the device's safety time limit. Check to ensure the flame is lit before placing any
control instrument in the flue. Adjust and check the gas flow necessary for the boiler at the meter. Adjust the air flow
according to the gas flow to obtain correct combustion.

IMPORTANT ADVICE

All adjustable parts must be fixed by the installer after making adjustments. Check flue combustion after each adjust-
ment. The CO
values must be approx. 9.7 (G20) 9.6 (G25 11.7 (l3B) 11.7 (l3P) and the CO must be less than 75
2
ppm.
WARNING:
in order to adjust combustion and thermal capacity correctly, the fumes must be analyzed using specific instruments.
Combustion and thermal capacity must be adjusted simultaneously, making sure that the values read are correct and in any
case, that they comply with the safety regulations in force.
THIS OPERATION MUST BE PERFORMED BY PERSONNEL WHO ARE PROFESSIONALLY QUALIFIED
AND AUTHORIZED BY ECOFLAM SPA.
Metano
CO
2
CO
<50 ppm
G.P.L.
CO
2
CO
<50 ppm
CONNECTION TO THE GAS PIPELINE

ELECTRICAL CONNECTIONS

START UP OF THE BURNER
ADJUSTING THE COMBUSTION
30
1,3
9,6%
1,25
25
20
1,2
15
1,15
11,7%
10
1,1
10
1,2
20
30
40 50 60
80
100
70
90
TH RMAL POW R (kW)
pag.8
200
300 400
600
800
1000
500
700
900
1,2
2000

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

Blu 700 pG20G25G30G31

Tabla de contenido