Changing The Assembly Location - Nussbaum SMART LIFT 2.30 SL Instrucciones De Servicio

Ocultar thumbs Ver también para SMART LIFT 2.30 SL:
Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

company then a specialist must be tasked with the
safety inspection.
The specialist confirms seamless operation of the lift
on the set up protocol for single safety inspection
and releases the lift for use.
After commissioning please complete the as-
i
sembly protocol and send to the manufacturer
immediately.
8.6

Changing the assembly location

To change the assembly location the pre-conditions
must be met according to the assembly guidelines.
The location change is to be done according to
the following sequence:
• Move the lift rails to about half height.
• Disconnect electrical supply lines to the lift from
mains power.
• Loosen cables between both columns.
• Remove the lifting arm (remove locking rings on
the lifting arm bolts,
• Pull out the lifting arm bolts and remove the lifting
arm).
• Loosen the anchor fastenings.
• Carefully transport the lift column using appropri-
ate auxiliary means (e.g. crane, forklift, etc.) to
the new assembly location.
• Assemble the lift according to the procedure
during assembly and anchoring before first com-
missioning.
Use new anchors. The old anchors are
no longer fit for purpose.
120
OPI_SMART LIFT 2.30 SL-2.35 SL-2.40 SL - HYMAX S 3000-S3500-S4000_V1.2_DE-EN-FR-ES-IT

Publicidad

Tabla de contenido
loading

Tabla de contenido