Commissioning and optimizing
the capacity controller
The controller is commissioned as described in chapter 5.
If possible, it should be commissioned using only pure superheat
control.
After optimizing the control parameters as described in section 5.5,
capacity control must be configured and parameterized. In principle,
the parameters (XP, TN) of the capacity controller are to be opti-
mized according to section 5.5. They must always be selected such
that they are considerably greater than the parameters of the super-
heat controller.
Superheat - CPS40
Controlling the cooling capacity