GAS BOILER SYSTEM COMMISSIONING CHECKLIST
This Commissioning Checklist is to be completed in full by the competent person who commissioned the boiler as a means of
demonstrating compliance with the appropriate Building Regulations and then handed to the customer to keep for future reference.
Failure to install and commission according to the manufacturer's instructions and complete this Commissioning Checklist will invalidate the
warranty. This does not affect the customer's statutory rights.
Customer name:
Address:
Boiler make and model:
Boiler serial number:
Commissioned by (PRINT NAME):
Company name:
Company address:
To be completed by the customer on receipt of a Building Regulations Compliance certificate*
Building Regulations Notification Number (if applicable)
CONTROLS (tick the appropriate boxes)
Time and temperature control to heating
Time and temperature control to hot water
Heating zone valves
Hot water zone valves
Thermostatic radiator valves
Automatic bypass to system
Boiler interlock
ALL SYSTEMS
The system has been flushed and cleaned in accordance with BS7593
What system cleaner was used?
What inhibitor was used?
Has a primary water system filter been installed?
CENTRAL HEATING MODE measure and record:
Gas rate
Burner operating pressure (if applicable)
Central heating flow temperature
Central heating return temperature
COMBINATION BOILERS ONLY
Is the installation in a hard water area (above 200ppm)?
If yes, and if required by the manufacturer, has a water scale reducer been fitted?
What type of scale reducer has been fitted?
DOMESTIC HOT WATER MODE Measure and Record:
Gas rate
Burner operating pressure (if applicable)
Cold water inlet temperature
Hot water has been checked at all outlets
Water flow rate
CONDENSING BOILERS ONLY
The condensate drain has been installed in accordance with the manufacturer's instructions and/or BS5546/BS6798
ALL INSTALLATIONS
At max. rate
Record the following:
At min. rate: (where possible)
The heating and hot water system complies with the appropriate Building Regulations
The boiler and associated products have been installed and commissioned in accordance with the manufacturer's instructions
The operation of the boiler and system controls have been demonstrated to and understood by the customer
The manufacturer's literature, including Checklist and Service Record, has been explained and left with the customer
Commissioning Engineer's Signature
Customer's signature
(To confirm satisfactory demonstration and receipt of manufacturer's literature
* All installations in England and Wales must be notified to Local Authority Building Control (LABC) either directly or through a Competent Persons Scheme. A Building Regulations Compliance
Certificate will then be issued to the customer.
Manual de instrucciones
14
Telephone number:
Gas Safe register number:
Telephone number:
Commissioning date:
Room Thermostat and programmer/timer
Load/weather compensation
Cylinder thermostat and programmer/timer
Fitted
Fitted
Fitted
Fitted
m³/hr
mbar
OR Gas inlet pressure at maximum rate
m³/hr
mbar
OR Gas inlet pressure at maximum rate
CO
ppm AND CO/CO
CO
ppm AND CO/CO
Programmable room thermostat
Optimum start control
Combination boiler
Not required
Not required
Not required
Not required
Not required
Yes
Quantity
Litres
Yes
No
OR
ft³/hr
mbar
°C
°C
Yes
No
Yes
No
OR
ft³/hr
mbar
°C
Yes
Temperature
°C
l/min
Yes
Ratio
2
Ratio
2
Yes
Yes
Yes
Yes
D2CND024A1/4AB + D2TND012~024A4AB
Caldera de condensación de montaje en pared
3P469438-3M – 2019.11

Hide quick links:

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

D2cnd024a4abD2tnd012a4abD2tnd018a4abD2tnd024a4ab

Tabla de contenido