Checking And Starting Up The Unit - EAS ELECTRIC EMCH Serie Manual De Instalación Y Manual De Usuario

Ocultar thumbs Ver también para EMCH Serie:
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

15. Checking and Starting Up the Unit

Preparing for first start up
Restart after shutting down for long periods.
The chiller must be started up for the first time by the Technical Service. Before starting up the chillers, make
sure that:
-
All safety conditions have been respected.
-
The chiller is adequately fixed to the surface it rests on.
-
Functional distances have been respected.
-
Hydraulic connections have been carried out as indicated in the manual.
-
The water circuit is filled and vented. When draining after heat pump operation, take care as the water
may be hot.
-
The water circuit valves are open.
-
Electrical connections have been carried out correctly.
-
Voltage is within a tolerance of 10% of the rated voltage for the unit.
-
The unit is correctly earthed.
-
All electrical and hydraulic connections are tight and have been completed correctly.
Use grommet A for the electrical power cable and grommet B for the other external wires.
50
A
B
V.2

Hide quick links:

Publicidad

Capítulos

Tabla de contenido
loading

Este manual también es adecuado para:

Emch-10w/1Emch-12w/1Emch-14w/3Emch-16w/3

Tabla de contenido