Installing Heat Reclaim Ventilation
2. Install the unit by hoist hook and check out whether ceiling is strong enough to hold the unit. In case of insufficient
strength, reinforce ceiling prior to installation.
Note: All above parts shall be procured in local region.
Preparation Prior to Installation
1. Decide on the relative positions of the unit and hoist hook. (Refer to installation diagram).
Set aside service space, including service port (open a service
port beside electrical cabinet on the ceiling to facilitate checking
and maintaining of air screen, heat exchange device and fan).
2. Make sure that external static pressure does not exceed range
limits.
3. Opening installing port: put signal transmission line and wire
control cable through the line hole on the unit after opening
installing port on the ceiling.
4. Keep ceiling in level position after opening installing port;
reinforce ceiling when necessary to prevent vibration.
(Concerned architect or carpenter can be consulted).
5. Installing Draw Bolt (Choose from the M10-M12 Range)
Installation Position
•
Please install in places capable of bearing unit weight. Improper installation is dangerous; it not only causes
vibration but produces operating noises.
•
Set aside service space and access hole. Please make sure that access hole is preset to check air screen, heat
exchange device and fan.
•
Do not install the unit directly on roof or wall; otherwise, the unit may directly touch roof or vibration will ensue.
Relative Positions of
the Unit and Draw Bolt
17
Ceiling
Bolt Sleeve
Long Nut or
Screw Sleeve
Draw Bolt
Unit