3 - INSTALLATION OF THE MOTOR
3.1 - POSITIONING OF THE MOTOR
To fix TORQ, follow the instructions below:
1.
use the measurements indicated in the drawing for the
foundations
2.
Arrange for one or two pipes for the passage of electric
cables
3.
Assemble the 2 clamps on the anchoring plate and fix them
with the 4 bolts issued with the motor
4.
Pour the concrete and position the anchoring plate
m
WARNING: check that the plate be on a perfectly
levelled surface and parallel to the gate
325 mm
20 mm
min 60mm
5.
Wait for the complete setting of the concrete
6.
Unscrew the bolts fixing the base to the clamps and put the
motor on the plate
7.
Insert the 4 grains with their nuts in the proper place.
Adjust the 4 grains to make the motor be perfectly levelled
8.
Control that the motor is perfectly parallel to the gate, then
insert the 2 washers R and lightly screw the 2 bolts D
m
WARNING: put the washer G into the hole for the
passing of the cables as shown in the picture. Pierce the
washer to let the cable to be connected to the control unit
pass, paying attention to the dimensions in order to avoid
the entrance of insects and other small animals.
- 31 -
G
D
R