6.2.4.2
Connection and configuration
Connecting the energy management system
u Install the energy management system in the
upstream electrical installation.
u Connect the energy management system and
the product with a data cable.
1 "5.7 Connecting the data line (Modbus RTU)"
[} 16]
Configuration
To set up an energy management system via Mod-
bus RTU, the following settings have to be made
using DIP switches:
DIP switch
Setting
(bank S1)
4
ON
5
ON
6.3
Switching on the product
The tasks described in this section may only
be carried out by a qualified electrician.
Requirement(s):
ü Product is installed correctly.
ü Product is not damaged.
ü The necessary protective devices are installed
in the upstream electrical installation in compli-
ance with the relevant national regulations.
1 "5.2.2 Protective devices" [} 13]
ü During the initial setting-up process, the product
was inspected in accordance with IEC 60364-6
and the applicable national regulations (e.g. in
Germany: DIN VDE 0100-600).
1 "6.4 Testing the product" [} 28]
u Switch on the power supply and check.
6.4
Testing the product
The tasks described in this section may only
be carried out by a qualified electrician.
28
Brief description
Using Modbus RTU
Satellite
u At initial start-up, test the product in accordance
with IEC 60364-6 and the applicable national
regulations (e.g. in Germany: DIN VDE
0100-600).
The test can be carried out in conjunction with the
MENNEKES test box and standard-compliant test
equipment. The MENNEKES test box simulates
vehicle communication. Test boxes are available as
an accessory from MENNEKES.
6.5
More settings
6.5.1 Description of the configuration tool
The basic settings can be made via DIP switches at
the charging station. The configuration tool is re-
quired for advanced settings.
On initial commissioning, on our website
under "Services" > "Software updates",
check whether there is a newer firmware
version of the product or configuration tool.
Update if necessary.
1 "8.3 Firmware update" [
34]
}