Once the modbus address has been changed, make sure that
3.
the inverter is configured according to the required functions:
Without zero injection.
d.
In order to view the consumption data provided by the SLC
ENERGY MANAGER<F in the APP, configure the following
inverter parameter:
General configuration → Power limit → make sure
that it is set to "OFF".
General configuration → Export → set to 100%.
The meter and the CT transformers must be
installed and connected, in accordance with
section "Alimentation des dispositifs."
With zero injection.
e.
The "Zero injection" function prevents the energy gener-
ated by the inverter that is not consumed in the same
installation from being fed into the grid. In other words,
it reduces the power of the inverter so that the generation
is adapted to the consumption.
To activate the function, follow these steps on the inverter
display:
General configuration → Power limit → make sure
that it is set to "OFF".
General configuration → Export → set to 100%.
Once configured, continue with section "6.  CON-
FIGURATION OF THE REMOTE CONNECTION OF THE
DEVICE", if you have configured the SLC ENERGY
MANAGER device and have access to the installa-
tion's plant, either via the APP or web page, continue
with section "9.2. INDIVIDUAL PLANT SCREEN"
The meter and the CT transformers must be
installed and connected, according to section
"Alimentation des dispositifs."
Once the previous section has been completed, connect the
4.
solar inverter's AC power supply.
Switch on the solar inverter's AC power switch.
For more information, Annex I contains a table with the
possible statuses of the LEDs of the SLC ENERGY
MANAGER unit with the respective descriptions for diag-
nosing possible errors.