Installation • Instalación
Installation • Instalação
1
2
3
4
wrong • no correcto
incorrect • incorrecto
6
5
6
correct • correcto
correct • correcto
1. Feed pipe and fitting at least ½"!
(internal dia > 0,5 inch)
2. No filters in feed line
3. Slope in feed line > %!
4. Only use ball valves!
5. Pressure: min. 12 psig or 18 psig!
(check type plate for correct pres-
sure)
6. Short pressure hose!
7. For each yard of rising slope in the
outlet line, the required minimum pres-
8
sure will increase by .5 psig.
7
The rise of the outlet line must not
exceed 7 feet!
8. Collecting line min. ½ '' with %
slope
9. In the case of inflow problems, install
venting line.
Note:
pressure differences!
Each condensate source must be drained
separately!
Note:
Venting!
If the feed line cannot be laid with suffi-
cient slope, it will be necessary to install
a venting line!
Note:
Deflector area!
If drainage is to take place directly from a
line, it is advisable to arrange the piping
so that the air flow is diverted.
ECO-DRAIN 13, 13 CO, 13 CO PN25