Novoferm NovoDock L150 Instrucciones De Montaje página 8

Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

5. Installing the fixed drawbridge leveller, type W
5.2
EN
5.3
Installation
First of all, check that the position where the drawbridge leveller is to be installed offers adequate free space for operation when in use.
Packing is required if there is a gap of more than 1 mm between the hinge plate (1) and the steel U profile (2).
The top joint along the entire length of the hinge plate should be prepared for a continuous weld.
Before welding, the zinc coating should be removed in the area of the welded joint.
The bottom welded joint should be welded alternately starting from the left and from the right (see figure).
A central weld where L=500 mm is required in the area of the hinge plate.
The side weld should be executed in accordance with the figure.
After welding, the attachment fittings should be removed and the welded seams protected against corrosion.
Painting welded and damaged surfaces:
5.4
Surfaces that are to be painted must be dry and free of dirt, grease, rust, etc.
Spray cold galvanising paint on the surfaces and allow to dry for approximately 30 minutes
After installation, apply a final coat of paint to all areas of paint damage using the touch-up paint provided.
5.5
Marshalling space
Adequate marshalling space must be provided for parking up materials handling equipment, if required
6
This installation manual must be given to the customer and kept safely during the entire period of use!
Instruction
1. Hinge plate
2. Steel U profile
All dimensions in mm
General instruction: The image may differ at detail level.

Publicidad

Tabla de contenido
loading

Tabla de contenido