10. Welding the guide profile in place for the drawbridge leveller, type Z

10.1
EN
10.2
Preparation
First of all, check that the position where the drawbridge leveller is to be installed offers adequate free space for operation when in use.
Make sure that the guide profile is completely straight before tack-welding it in place. When tack-welding the profile in place, make
sure that the vertical axis of the guide profile is perfectly vertical.
Packing is required if there is a gap of more than 1 mm between the guide profile (1) and the steel U profile (2).
Before welding, the zinc coating should be removed in the area of the welded joint.
The guide profile must be attached in the horizontal position to the steel U profile with individual tack welds.
Important!
The guide profile must be perfectly level and perpendicular!
The guide profile (1) must then be welded along its entire length to the steel U profile (2), starting from the middle and in accordance
with the figure.
All of the slotted holes must be welded as shown.
12
This installation manual must be given to the customer and kept safely during the entire period of use!
1 Guide profile
2 Steel U profile (third-party supply)
3 End stop (not in scope of supply, responsibility of installer)
All dimensions in mm
General instruction: The image may differ at detail level.