Sump Pit Installation
Flow
Directional
Arrow
2" Checkvalve
Do Not Mount
Vertically
30"
18"
Figure 1
Pi ping – Sewage Applications (2" or
Less Solids)
In any case, piping must not be smaller than pump
discharge. When installed in a sewage system, pipe must
be capable of handling semi-solids of at least 2" (5.1 cm)
diameter.
The rate of flow in the discharge pipe must keep any
solids present in suspension in the fluid. To meet
minimum flow requirements (2 feet (.6 m) per second in
discharge line), size pipe as follows:
A Pipe Size Of:
1-1/2" (3.8 cm)
2" (5.1 cm)
2-1/2" (6.3 cm)
3" (7.6 cm)
NOTICE Use PTFE tape on pipe connections. Do not
use ordinary pipe joint compound on plastic pipe or
pump. Pipe joint compound can attack plastics and
damage pump.
3. To reduce motor noise and vibrations, a short length
of rubber hose can be connected into discharge line
near pump using suitable clamps.
For parts or assistance, call Flotec Customer Service at 1-800-365-6832.
115V Properly
Grounded
Outlet
Sump Pit
2" Discharge
Pipe
Be sure the
float switch can
swing through
it's entire arc.
Drill a 3/16"
vent hole here.
Install pump on
a hard, level surface.
Will Handle a Flow Rate Of:
12 GPM (45 LPM)
21 GPM (79 LPM)
30 GPM (113 LPM)
48 GPM (181 LPM)
4. If the pump discharge line is exposed to outside
subfreezing atmosphere, then the portion of line
exposed must be installed so any water remaining in
pipe will drain to outfall by gravity. Failure to do this
can cause water trapped in discharge to freeze which
could result in damage to pump.
5. Install a 2" check valve in the horizontal portion of
the discharge pipe. Make certain, the flow indicating
arrow, points away from the pump. This check valve
will keep the water from either running back into the
basin or into the area being pumped out when the
pump is not running. Check valve should be a free
flow valve that will easily pass solids.
NOTICE For best performance of check valve when
handling solids, do not install it with discharge angled
more than 45° above the horizontal. Do not install check
valve in a vertical position as solids may settle in valve
and prevent opening on startup.
6. Drill a 3/16" (4.7mm) hole in discharge pipe
about 1"-2" (2.5 - 5.1cm) above pump discharge
connection (but below check valve) to prevent
airlocking the pump.
7. Insert the float switch piggy-back plug into a properly
grounded outlet and the pump plug into the piggy-
back plug.
8. Check the installation by observing the pump
operation through one complete cycle. Make sure
that no parts of the assembly interfere with the
float switch.
Risk of flooding . Can cause personal injury
and/or property damage. Failure to make this operational
check may lead to improper operation, premature failure,
and flooding.
Electrical
Risk of electric shock . Can shock, burn or
kill. When installing, operating, or servicing this pump,
follow safety instructions listed below.
1. DO NOT splice the electrical power cord.
2. DO NOT allow electrical cord plug to
be submerged.
3. DO NOT use extension cords. They are a fire hazard
and can reduce voltage sufficiently to prevent
pumping and/or damage motor.
4. DO NOT handle or service pump while it is
connected to power supply.
5. DO NOT remove grounding prong from plug or
modify plug.To protect against electrical shock, the
power cord is a three-wire conductor and includes
a 3-prong grounded plug. Plug pump into a 3-wire,
grounded, grounding-type receptacle. Connect pump
according to electrical codes that apply.