6. Installation

Unless otherwise specified, all measurements are expressed in millimetres (mm).

6.1 Preliminary checks

Check that the structure is sufficiently sturdy and that the hinge pivots are properly lubricated.
Provide an opening and closing stop.
Note: if the gate wing is more than 2.5 m wide, an electric lock should be installed.

6.2 Foundation case installation

Install the foundation case as indicated in the relevant manual.

6.3 Lever mechanisms installation

Choose and install the lever mechanisms as indicated in the relevant manual.

6.4 Wing release installation

Choose and install the door release mechanisms as indicated in the relevant manual.
WARNING: to install the releases more easily, we advise you to position the gate at the centre of the
foundation casing and remove the lid, in such a way as to have enough space for fixing the screws.

6.5 Geared motor installation

After installing the foundation casing, the respective lever and release mechanisms go before the
installation of the gear motor as shown in the figure. NOTE: the figure shows the motor installed
on the right door wing.
Carefully clean the bottom of the foundation casing from dirt or cement to guarantee an even
laying of the gearmotor.