Shielding And Cable Routing - Balluff BML-S1F Serie Instrucciones Breves

Sistema de medición de desplazamiento incremental de codificación magnética
Ocultar thumbs Ver también para BML-S1F Serie:
Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 18
BML-S1F_-A/Q _ _ _ -M_ _ 0 - _ 0-...
Incremental Magnetic Linear Encoder

Shielding and cable routing

Defined ground!
The position measuring system and the control
cabinet must be at the same ground potential.
Shielding
To ensure electromagnetic compatibility (EMC), observe
the following:
The cable shield must be grounded on the controller
side, i.e. connected to the protective earth conductor.
When ducting the cable between the sensor, controller,
and power supply, it is important to avoid going near
high voltage cables due to interferences. Stray noise
from AC harmonics (e.g. from phase angle controls or
frequency converters) are especially critical and the
cable shield offers very little protection against this.
Magnetic fields
The position measuring system is a magnetically coded
system. It is important to maintain adequate distance
between the position measuring system and strong,
external magnetic fields.
Cable routing
Do not route the cable between the position measuring
system, controller, and power supply near high voltage
cables (inductive stray noise is possible).
The cable must be routed tension-free.
Cable length
Max. cable length 20 m. Longer cables may be used if
their construction, shielding and routing prevent noise
interference.
www.balluff.com
Startup
DANGER
Uncontrolled system movement
When starting up, if the position measuring system is
part of a closed loop system whose parameters have not
yet been set, the system may perform uncontrolled
movements. This could result in personal injury and
equipment damage.
► Persons must keep away from the system's
hazardous zones.
► Startup must be performed only by trained technical
personnel.
► Observe the safety instructions of the equipment or
system manufacturer.
1. Check connections for tightness and correct polarity.
Replace damaged connections or devices.
2. Turn on the system.
3. Check measured values in the controller and reset if
necessary.
english
4