Generator Connections - Generac CorePower 5837 Lineamientos De Instalación

Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

GENERATOR CONNECTIONS

1. Remove one of the ¾" knockouts from the side or bottom of
the transfer switch enclosure.
2. Feed the power and control wires from the generator into
the transfer switch enclosure and secure the conduit using a
suitable conduit connector and locknut.
3. Cut to length, strip and attach generator power wires to
Generator source connections in the Transfer Switch
4. Cut to length, strip, identify and attach generator sensing
wires marked N1, N2 & T1 to correspondingly marked Fuses
in the Transfer Switch.
5. Cut to length, strip, identify and attach transfer switch
control wires marked 23, 15B & 0 to XFER, BAT + and
BAT – terminals respectively on the transfer switch control
mechanism.
XFER
BAT+
BAT -
6. Cut to length, strip and attach remaining neutral and ground
wires to the loadcenter grounding bars.
7. Move all the circuit breakers in the load center to the OFF or
OPEN position.