All manuals and user guides at all-guides.com
Prepare the Site - Deck-Mount Installation (cont.)
Verify the diameter of the drilled holes will accommodate the
diameter of the tubes. Adjust the hole diameter slightly, if needed.
Secure the support plate to the bath deck with the eight wood
screws (provided).
Solder a 1/2" male copper connection to the outside of a 12" (30.5
cm) section of each water supply line.
Apply thread sealant to each male copper connection.
Securely tighten the coupling assemblies to each male copper
connection.
Thread the tubes into the support plate.
Place a washer and nut over the tubes, both above and below the
deck.
Hand tighten the nuts.
Verify the top of the tube is flush with the surface of the intended
finished deck height.
Securely tighten the nuts with a wrench.
Connect the supply lines under the deck to the main water
supply.
Insert the plastic pipe plugs into the coupling assemblies.
Turn on the water supply.
Check all connections for leaks. Adjust as needed.
Turn off the water supply, then remove and discard the plastic
pipe plugs.
Finish the bath deck and surround.
Kohler Co.
13
1054455-2-B