4. Installing the refrigerant piping
=
A+a+b+c+d
120m
L = A+d
=
80m, R= d
H
=
30m (Outdoor lower H
=
h
12m
A
L
r
B
b
a
c
C
C
C
Fig. 4-1
A
45°±2°
A Flare cutting dimensions
B Flare nut tightening torque
Fig. 4-2
A (Fig. 4-2)
Copper pipe O.D.
Flare dimensions
(mm)
øA dimensions (mm)
ø6.35
ø9.52
12.8 - 13.2
ø12.7
16.2 - 16.6
ø15.88
19.3 - 19.7
B (Fig. 4-2)
Copper pipe O.D.
Flare nut O.D.
(mm)
ø6.35
ø6.35
ø9.52
ø12.7
ø12.7
ø15.88
ø15.88
A
Fig. 4-3
6
A+B+C+a+b+c+d
=
120m
L = A+B+C+d
=
80m
R= B+C+d
=
30m
H
=
30m (Outdoor lower H
h
=
12m
A
L
r
d
B
C
B
a
b
c
C
C
C
=
30m
=
20m)
A : Outdoor Unit
B : First Branch
C : Indoor unit
d
C
B
C
D
8.7 - 9.1
Tightening torque
(mm)
(N·m)
17
14 - 18
22
34 - 42
22
34 - 42
26
49 - 61
29
68 - 82
29
68 - 82
36
100 - 120
A
A Die
B Copper pipe
B
A
PUMY-P100-140
=
20m)
B, C, D
Ç Total capacity of indoor units
a, b, c, d, e, f
Î Model number
20, 25, 32, 40, 50
63, 80, 100, 125, 140
C
Ï 4-Branching header
CMY-Y64-G-E
4.2. Connecting pipes (Fig. 4-2)
Fig. 4-1 is a sample of piping system.
• When commercially available copper pipes are used, wrap liquid and gas pipes
with commercially available insulation materials (heat-resistant to 100 °C or more,
thickness of 12 mm or more).
• The indoor parts of the drain pipe should be wrapped with polyethylene foam insu-
lation materials (specific gravity of 0.03, thickness of 9 mm or more).
• Apply thin layer of refrigerant oil to pipe and joint seating surface before tightening
flare nut. A
• Use two wrenches to tighten piping connections. B
• Use leak detector or soapy water to check for gas leaks after connections are com-
pleted.
• Apply refrigerating machine oil over the entire flare seat surface. C
• Use the flare nuts for the following pipe size. D
Gas side
Pipe size (mm)
Liquid side
Pipe size (mm)
• When bending the pipes, be careful not to break them. Bend radius of 100 mm to
150 mm is sufficient.
• Make sure the pipes do not contact the compressor. Abnormal noise or vibration
may result.
1 Pipes must be connected starting from the indoor unit.
Flare nuts must be tightened with a torque wrench.
2 Flare the liquid pipes and gas pipes and apply a thin layer of refrigeration oil
(Applied on site).
• When usual pipe sealing is used, refer to Table 1 for flaring of R410A refrigerant
pipes.
The size adjustment gauge can be used to confirm A measurements.
Table 1 (Fig. 4-3)
Copper pipe O.D.
(mm)
ø6.35 (1/4")
ø9.52 (3/8")
ø12.7 (1/2")
ø15.88 (5/8")
Å Liquid pipe
ı Gas pipe
ø9.52
ø15.88
Å Liquid pipe
ı Gas pipe
ø9.52
ø15.88
Å Liquid pipe
ı Gas pipe
ø6.35
ø12.7
ø9.52
ø15.88
‰ Branch kit model
CMY-Y62-G-E
Ì 8-Branching header
CMY-Y68-G-E
Indoor unit
20-50
63-140
ø12.7
ø15.88
ø6.35
ø9.52
A (mm)
Flare tool for R410A
Flare tool for R22·R407C
Clutch type
0 - 0.5
1.0 - 1.5
0 - 0.5
1.0 - 1.5
0 - 0.5
1.0 - 1.5
0 - 0.5
1.0 - 1.5
(mm)
(mm)
(mm)
Outdoor unit
100-140
ø15.88
ø9.52