Section 7 - Quick Setup Commissioning; Physical Checks; Pressure Display; Quick Set-Up Configuration - Ingersoll Rand System Automation X4I Manual De Configuración Rápida

Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 77
SECTION 7 — QUICK SETUP COMMISSIONING
When commissioning the X4I, carry out the following
procedures before attempting to start. It is
recommended that an authorized and trained Service
Technician performs the commissioning.
The Quick Setup Manual allows the user to enter the
basic required parameters to quickly start sequencing
the compressors with the X4I. Once sequencing and
basic control is established, the user can refer to the
Operator's Manual for more detailed information on
other features and functionality of the unit.

PHYSICAL CHECKS

1. Before applying power to the X4I, ensure that the
power supply connections are correct and secure
and that the operating voltage selector is set
correctly for the power supply voltage in use:
115Vac or 230Vac (+-10%), 50/60Hz.
2. Open the front panel of the X4I and check the
location of the link wire(s) connected to the
"Voltage Selection" terminals of the power supply
PCB. If necessary, change the link wire locations
to those illustrated for the voltage in use.
See the INSTALLATION section in the
Operator's Manual for more information.
3. Switch on the power supply to the unit.
The control program identification will be displayed for a
short period followed by the normal operational user
display.
All manuals and user guides at all-guides.com
11

PRESSURE DISPLAY

Check the displayed system pressure. If the pressure is
incorrect, or inaccurate, check the type and range of the
sensor and carry out the pressure sensor commissioning
and calibration procedure. If the display shows an error,
the error will need to be corrected before continuing.
See the Operator's Manual for troubleshooting and
correcting the fault or error condition.

QUICK SET-UP CONFIGURATION

Before successful basic operation can be established the
following items must be set (in the order show) to suit
installation requirements. The X4I can easily be
commissioned by simply setting the following
parameters.
NOTE: Leave all other parameters at factory defaults.
S02 – NC
Number of Compressors
S02 – PM
Maximum Pressure Alarm
S01 - Ct
Real Time Clock Set
C02 –01 to 04
Compressor #1 to 4 Configuration
T01 – PH
High Pressure Set Point
T01 – PL
Low Pressure Set Point
T01 – Pm
Minimum Pressure Alarm
NOTE: By default, the pressure unit of measurement is
PSI. If the unti of measurement is BAR or kPA, please
refer to the Operator's Manual for information on
changing the S02 P> Units Setting parameter.
Once set, the X4I will sequence all compressor based on
load demand (First In / Last Out) and will rotate them
once per week on Monday at 00:00 hours.

Publicidad

Tabla de contenido
loading

Tabla de contenido