In case of multiple inverters, reserve speciûc clearance between the inverters (Fig. 4-5).
In case of back-to-back installation, reserve speciûc clearance between the two inverters (Fig. 4-6).
Install the inverter at an appropriate height for ease of viewing LED indicators and operating switches.
4.3
Moving the ZGR SOLAR STR 250
Move the inverter to the speciûed position before installation. The inverter can be moved manually or via a hoist.
4.3.1 Manual Transport
Use the handles on the backplane and base to transport the inverter to the destination.
CAUTION
Inappropriate moving operation may cause personal injury!
It is recommended that at least four installers carry the inverter together and wear protective equipment such as
smash-proof shoes and gloves.
Always beware of the gravity center of the inverter and avoid tipping.
Operation manual
Fig. 4-4 Clearance around the ZGR SOLAR STR 250
Fig. 4-5 Clearance around multiple inverters
Fig. 4-6 Clearance between the two inverters back-to-back
www.zigor.com
14

Publicidad

loading

Productos relacionados para ZIGOR ZGR SOLAR STR 250