5.8 Function test after installation
1. Establish the voltage supply.
2. Check functions
Installation was carried out correctly if the following statuses of the controller LEDs apply to the
WTC 200:
• LEDs for power supply light up (LED 15, 16, 17).
• All LEDs for the open input port contacts light up (LED 10, 11, 12, 13).
• The LEDs for the closed input port contacts do not light up (LED 10, 11, 12, 13).
• The LEDs for the RS-485 interfaces do not flash or light up in red if no bus participant is
connected yet (LED 1, 2, 4).
• Status LED 6 is off.
• Network connection LED lights up (yellow LED at network connection "C").
The system configuration and the configuration of the Micro SD cards take place
via Dialock software 2.0 and is carried out by the system supplier's customer service.
The initial start-up of the access control system is also carried out by the system
supplier's customer service.
More information about commissioning and configuration of the SD card and the
overall system can be found in the Dialock 2.0 software manual.