▶ Install the charging pedestal on a firm surface
in a location protected from rain. Avoid locations
with direct exposure to sunlight.
▶ When using the 2.5 m-long vehicle cable, install
the charging pedestal as close to the vehicle
as possible. Bear in mind your preferred parking
position and vehicle orientation.
▶ Do not install the charging pedestal:
– in potentially explosive atmospheres
– in the way of emergency or recovery services
or walkways (also make sure the cable does
not cross these routes)
– in locations exposed to hose water (e.g. from
pressure washers or garden irrigation)
– under hanging objects
– in stables, barns and other places where
ammonia gas occurs
Recommended installation
sequence
1. Prepare the foundation (with anchor rods).
2. Lay the cable from the circuit breaker to the
foundation.
3. Install the charging pedestal.
4. Have the power supply installed by a qualified
electrician.
Preparing the foundation
▶ For secure fastening: Check the condition of the
foundation before installation!
If a firm surface with sufficient load-bearing capacity
as per the static calculation is available and the cable
can be routed correctly, you do not need to produce
a separate foundation. In this case, you can install the
charging pedestal directly on the existing surface.
Installation on an existing surface
1. Mark drill holes on the ground for the cable entry.
2. Drill holes with ø 14 mm and insert the founda-
tion fastening kit as described in the product
manual.
Fig. 2: Drilling dimensions
Installing the charging pedestal
▶ Produce the foundation at the site in the correct
manner.
Secure with Hilti HVA, for example (see Appendix:
Hilti Foundation Fastening Kit on page 23) or similar.
Information
The charging pedestal is generally installed directly
(without clearance) on prepared reinforced concrete
surfaced with plaster, tarmac or similar.
If the surface is to be finished later, installation with
ground clearance is possible, so that the charging
pedestal can be installed above the planned surface
in advance (see Fig. 3).
Preparing for installation
with clearance
1. Check that the anchor rods are seated correctly.
2. Adjust the desired height to between 20 mm and
50 mm with the aid of four M12 hexagon nuts
and A13 washers.
1
2
≤ 50 mm
Fig. 3: Installation with clearance