Lowering The Vehicle; Balance The Drive Rails; Maintenance And Care Of The System; System Maintenance Plan - ATT Nussbaum JUMBO LIFT 3200 NT Instrucciones De Servicio

Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

• Lift the vehicle. Push the
• If the wheels are not blocked, interrupt the lifting
process and check for proper seating of the po-
lymer overlays.
• Raise the vehicle to the desired working height.
Push the
o
„Lift" (2) button.
5.3

Lowering the vehicle

• Inspect the hazardous area.
No person or object may stand in the working
area of the lift, or on the lift.
The vehicles cannot be lowered into the lowest
!
position without wheels. Otherwise the lift can-
not raise the load using its own force. The vehi-
cle could be damaged.
• Lower the vehicle to the desired working height
or completely lower it. Push the
button (see figure 003).
• The entire lowering process must be observed.
• If the lift is in the detectable lowest position, re-
move the polymer overlays and drive the vehicle
from the lift.
5.4

Balance the drive rails

See „Section 4.3 filling and venting the hydraulic
system".
6
Maintenance and care of the sys-
tem
Before maintenance, do all preparati-
on work so there is no danger to life or
limb or object damage during mainte-
nance and repair work.
Value is placed on long lifetimes and safety in
the development and production of Nußbaum
products. To guarantee the safety of the opera-
tor, product reliability, low running costs, keep the
warranty and also the long-lifetime of the product,
proper set up and operation is just as important as
regular maintenance and sufficient care.
Our platforms fulfil or exceed all safety standards
of the countries we supply to. For example, Eu-
ropean regulations require a service by qualified
experts every 12 months of work of the platform.
52
o
„Lift" (2) button.
u
„Lower" (3)
JUMBO LIFT 3200 NT - HYMAX XX 3200 PH
To guarantee the largest possible availability and
functional capacity of the lift system, ensure the
list of any cleaning, care and maintenance work
is done.
The lift system is to be serviced at regular intervals
according to the following plan. For intensive ope-
ration and higher degree of contamination shor-
ten the service interval.
The complete function of the lift system is to be
observed during daily use. Customer service must
be informed of any malfunctions or leaks.
To simplify maintenance work, follow instructions
on the maintenance sticker that is found some-
where on the unit, depending on the lift design.
6.1

System maintenance plan

Before beginning service, disconnect
from power. The system is to be se-
cured against unintentional lowering
and unauthorized access.

6.1.1 As required or visible damage

• Check the polymer overlays and replace if re-
quired.

6.1.2 Maintenance 1 x per year

• Check condition of the model plate, load capa-
city and sticker. Exchange them if damaged or
illegible.
• Free the piston rod of the lifting cylinder of sand
and dirt.
• Check the wiper for damage.
• Moving parts such as joint bolts and DU bearings,
sliding pieces, sliding surfaces and rollers are to
be cleaned and checked for wear, exchange
if required.
• Lubricate all lubrication nipples with an acid-free
multi-purpose grease. Do not over-lubricate.
• All weld seams must have a visual inspection.
Stop the system and contact the manufacturer if
there are cracks or breaks in weld seams.
Version 1.0
20110009 OPI

Publicidad

Tabla de contenido
loading

Productos relacionados para ATT Nussbaum JUMBO LIFT 3200 NT

Este manual también es adecuado para:

Nussbaum hymax xx 3200 ph

Tabla de contenido