Commissioning
Combination elec-
trode K 800
General informa-
tion
Before measuring
18
Commissioning
1
Remove the storage vessel.
2
Fill ELY/BR/503/K bridge electrolyte into the filling opening so that
the inner junctions are covered with bridge electrolyte.
3
Rinse the combination electrode with deionized water.
4
Wipe the shaft using a clean paper towel.
Conditioning, calibration, measurement
When operating the electrode ensure that
 the filling opening (1) for the bridge electrolyte is open
 the inner junctions (3) are covered with bridge electrolyte
 no air bubbles are in the bridge electrolyte
the depth of immersion is within the optimum range:
Minimum depth of immer-
sion
Maximum depth of im-
mersion
1
Condition every ion sensitive electrode in standard solution before
using it.
1
2
3
4
The outer junction (4) must be covered
Approx. 1 cm below the fluid level (2) of the
bridge electrolyte
K 800
ba15360d04