REPAIR ( CONTINUED )
Inspect and Replace Power Switch
1.
Turn the pump OFF and disconnect from power.
2.
Remove the switch coverplate from the pump housing.
3.
Inspect wiring in both cavities for loose connections. Make sure switch
toggle moves to the ON and OFF positions easily.
4.
To replace the switch, remove the Torx head screw, then remove the switch
assembly (see Figure 7).
5.
Unscrew both blade terminals and remove red pump wires from the back of
the switch (see Figure 8).
6.
Install a new switch by reversing the above procedure. Make sure switch
toggle is in the OFF position between the switch lever and replace switch
coverplate (see Figure 9). Make sure the O-ring is seated properly before
tightening the switch coverplate.
Figure 7
Figure 9
Replace Motor
In order to preserve the UL Listing or CSA Certification for pump safety, return
the entire pump to the factory for motor repair or replacement. For products
serviced outside the factory, the UL and CSA nameplates must be defaced to
indicate the equipment may no longer meet the requirements for UL Listing or
CSA Certification. This does not apply to products serviced outside the factory
under the UL program for Rebuilt Motors for Use in Hazardous Locations and the
CSA rebuild program.
10
EN
Torx Screw
Switch Lever
Figure 8

Publicidad