7.4 FINAL CHECK OF THE INSTALLATION
Before to proceed with the electrical cabling of the motor, check the correct movement of the gate:
1. Unlock the motor and move manually the wing of the gate (see related paragraph)
2. If the wing moves easily, the installation is correct. Otherwise lubricate the hinges, the hole in the front plate and the towing
of the gate. Check the correct installation of the motor.
8. CONNECTIONS AND CABLE SECTIONS
230V
4 x 0,75 mm
4 x 0,75 mm
3 x 1,5 mm
Line 230V
6-1624846
rev. 16
24V
Control unit
230V: 4 x 1,5 mm
2
24V: 2 x 1,5 mm
2
RX photocell
2
2
2
13/11/2018
230V: 4 x 1,5 mm
24V: 2 x 1,5 mm
2 x 0,75 mm
2
TX photocell
2 x 0,75 mm
2
Fig. 12
2
2
MOTOR CABLES [230V] TABLE
Black
Phase 1
Brown
Phase 2
Grey or light blue
Common
Yellow/Green
Ground