EXCLUSIVE GREEN HE C.S.I. - R.S.I.
3 - HYDRAULIC CONNECTIONS
Position and dimensions of hydraulic connections are specifi ed in fi gure 1.1:
A - CH return
3/4"
B - CH delivery
3/4"
C - Gas connection 3/4"
D - DHW outlet
(C.S.I)
1/2"
E - DHW inlet
(C.S.I)
1/2"
F - Support plate
G - Pre-installation template
4 - INSTALLING THE EXTERNAL PROBE
The sensor (Fig. 1.6) must be installed on an external wall of the building
you want to heat, while taking care to comply with the instructions below:
- It must be fi tted on the facade most often exposed to wind, on a wall facing
NORTH or NORTH-WEST, and taking care to avoid direct sunlight.
- It must be fi tted about 2/3 up the height of the façade.
- It must not be near any doors, windows, outlets for air ducts, or near
chimneys or other heat sources.
The electrical connection to the external sensor must be formed using a two-
pole cable (not supplied), with a cross-section of 0,5 to 1 mm
length of 30 metres. It is not necessary to worry about the polarity of the cable
for the connection to the external sensor. Do not form joints in this cable.
If a joint has to be made it must be watertight and adequately protected.
Any conduiting used for the connection cable must be separate from the
conduits used for the power cables (230 Vac).
WALL MOUNTING OF THE EXTERNAL SENSOR.
Install the probe in an area of smooth wall; for brick walls or other irregular
surfaces, prepare a smooth contact area if at all possible.
Remove the upper plastic cover by turning it anti-clockwise.
Identify the wall fi xing point and drill a hole for the 5x25 expansion grip.
Insert the expansion grip into the hole.
Remove the card from its housing.
Fix the housing to the wall using the supplied screw.
Attach the bracket and tighten the screw.
Loosen the cable grommet screw, push in the probe connection cable and
connect it to the electrical terminal.
Remember to fi rmly secure the cable grommet to prevent humidity from
entering.
Put the card back into its housing.
Close the upper plastic cover by turning it clockwise. Firmly secure the cable
grommet.
5 - CONDENSATE COLLECTION
The outlet collector A (Fig. 1.7) collects: the condensate water, any evacuation
water from the safety valve and the system outlet water.
The collector must be connected, by means of a rubber pipe (not sup-
plied), to a suitable collection and evacuation system in the storm water
outlet and in compliance with current regulations.
The external diameter of the collector is 20 mm: we therefore suggest
using an Ø 18-19 mm pipe, to be closed with a suitable clamp (not
supplied).
The manufacturer is not responsible for any damage caused by the lack
of a collection system.
The outlet connection line must have a guaranteed seal.
The manufacturer of the boiler is not responsible for any fl ooding caused
by interventions of the safety valve.
6 - GAS CONNECTION
Before connecting appliance to gas pipe network, check the following:
- regulations in force are met
- gas type used is the same as set for appliance operation
- pipes are clean.
Gas must be piped externally. If the pipe goes through a wall it must go through
the central opening in the lower part of the template. It is recommended to
install an appropriately sized fi lter on the gas line in case gas from the mains
contains some small solid particles. After installation make sure that all the
joints have been made airtight conforming to standard installation practices.
6
RB = water tank return 3/4" (R.S.I.)
MB = water tank delivery 3/4" (R.S.I.)
2
and a maximum
7 - ELECTRIC CONNECTION
To access the electrical connections, proceed as follows:
- unscrew the lower cover fi xing screw C, (Fig. 1.4)
- pull the cover towards you and remove (A-B) (Fig. 1.5)
- loosen the fi xing screws (D) and remove the shell (Fig. 1.2)
- lift up the panel and turn it forwards
- open the terminal board covers making them slide in the direction of the
arrows (Fig. 1.8: E high voltage connections 230 V, F low voltage connec-
tions, G water tank sensor connections only GREEN R.S.I.).
Connect the appliance to the mains power supply with a switch featuring a
distance of at least 3,5 mm (EN 60335-1, category III) between each wire.
The appliance uses alternating current at 230 Volt/50 Hz, has a power input
of 88 W (25kW C.S.I. - 25kW R.S.I.) and 116 W (35kW R.S.I. - 35kW C.S.I.)
and complies with EN 60335-1 standard. Connect the boiler to a safe earth
circuit according to current legislation.
Live and neutral (L-N) connections should also be respected.
The boiler can operate with phase-neutral or phase-phase power supply. For
fl oating power supply, without an earth-bonded conductor, it is necessary to
use an insulation transformer with secondary anchored to ground.
The earth conductor must be a couple of cm longer than the others.
Gas and/or water pipes may not be used to earth electrical equipment.
The installer is responsible for making sure that the appliance has an
adequate earthing system; the manufacturer shall not be held liable
for eventual damages caused by incorrect usage or failing to earth the
boiler.
Use the supplied power cable to connect the boiler to the mains power
supply.
Connect the ambient thermostat and/or time clock as shown in the electrical
diagrams.
When replacing the power cable, use a HAR H05V2V2-F cable, 3 x 0,75
mm
2
, Ø max. external 7 mm.
8 - FILLING AND EMPTYING THE SYSTEM
The central heating system can be fi lled up once the water mains have been
connected up.
This must be done while the installation is cold by:
- turn the caps of the lower (A) and upper (E) automatic bleed valves two
or three times; leave A and E valve caps open for continual air venting
(Fig. 1.9);
- making sure the cold water inlet tap is open
- opening the fi lling tap (B, on the boiler for GREEN C.S.I., external for
GREEN R.S.I.) until the pressure on the hydrometer (C) is between 1 and
1,5 bar (blue zone) (Fig. 1.9).
Close the fi lling tap after fi lling it up.
The boiler is equipped with an effi cient air separator so that there is no need
to do anything manually.
The burner only ignites when air venting has fi nished.
NOTE: air extraction from the boiler takes place automatically, through two
automatic bleeding valves, A and E.
The fi rst is situated on the pump, while the second is inside the air chamber.
NOTE (GREEN C.S.I. only): the boiler is also equipped with a semi-automatic
fi lling system. The fi rst system-fi lling operation must be carried out by opening
tap B with the boiler turned off.
NOTE (GREEN R.S.I. only): manual fi lling tap is not supplied with the boiler,
foresee one external or verify if external water tank has one.
Before starting to empty it, remove the electrical feeder by positioning the
general switch for the system on "off".
- Close the interception devices for the thermal system
- Loosen the system outlet valve (D) manually
- The water from the system is discharged through the outlet collector (F).
DHW system emptying (GREEN C.S.I. only)
The hot water system must be emptied every time there is risk of freezing by:
- turning off the tap at the mains
- turning on all the hot and cold taps
- emptying out the lowest parts of the system.