7. Commissioning, operation / 8. Maintenance and cleaning
Permissible vibration load at the installation site
The instruments should always be installed in locations free from
vibration.
If the pipe to the gauge is not rigid enough for a vibration-free
installation, the gauge should be mounted by means of mounting
devices for surface or pipe mounting, and, if necessary, with a capillary.
If necessary, it is possible to isolate the instrument from the mounting
point by installing a flexible connection line between the measuring
point and the pressure gauge and mounting the instrument on a suitable
bracket.
If this is not possible, the following limit values must not be exceeded:
Frequency range < 150 Hz
Acceleration < 0.5 g (5 m/s
Commissioning
During the commissioning process pressure surges must be avoided at all
costs. Open the shut-off valves slowly.

8. Maintenance and cleaning

8.1 Maintenance
The instruments are maintenance-free.
The indicator and switching function should be checked once or twice
every year. The gauge must be disconnected from the process to check
with a pressure testing device.
Repairs are only to be carried out by the manufacturer or appropriately
trained skilled personnel.
WIKA operating instructions models PGS10, PGS11 and PGS21
)