Descargar Imprimir esta página

Ecoflam MINOR 4 SP 30 Manual Del Usuario página 10

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

GB
BM2
BURNER START-UP
Once connected the hoses to the oil pipes make sure that there are no leakages. Air bleed the pipe through the
pump operating on the gauge connection (see fig.). Install the suitable nozzle for the needed capacity. Turn
thermostat to the desired temperature. The burner will purge for about 13 sec.( 20 sec. in case of BRAHMA
control box). At this point the oil valve opens and the transformer ignites.
Control the pressure on the pump. (see fig.). Adjust the needed quantity of air, operating on the air regulator.
In case of no ignition the burner goes to lock-out within 10 sec.
AIR REGULATION
FIRING HEAD SETTING
BLAST TUBE DISASSEMBLY
NOZZLE REPLACEMENT
Use only the box wrench provided for this operation. Remove the nozzle carefully taking great care not to
damage the electrodes. Fit the new nozzle with the same care.
NOTICE : Always check the position of the electrodes after replacing the nozzle(see plan).
2 ÷ 3 mm
3 mm
5/6 mm
pag.10

Publicidad

loading