Electrical Operation; Extraction/Insertion Procedures - WEG ABW Serie Manual De Instrucciones

Ocultar thumbs Ver también para ABW Serie:
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

www.weg.net

3.2. eleCtrICAl operAtIon

The operation of the circuit breaker by electrical control is executed by means of
the motorized drive and by the closing and opening coils, accessories installed
internally in the circuit breaker.
The motorized drive loads the springs of the operation mechanism automatically,
whenever the circuit breaker is turned off, an operation which ends after approximately
5s. The power supply of the motor is executed by the terminals U1 and U2.
In order to turn on the circuit breaker, when its springs are loaded, a voltage pulse
is applied to the terminals of the closing coil (A1 and A2).
In order to turn off the circuit breaker, a voltage pulse is applied to the terminals of
the opening coil (C1 and C2). In circuit breakers equipped with a subvoltage coil, the
circuit breaker can be turned off cutting the power supply of this coil (D1 and D2).

3.3. extrACtIon/InSertIon proCeDureS

3.3.1. Insertion
Lock of the
1. Pull the rails of
both the sides,
as far out as
possible.
4. Maintaining the OFF button
pressed, insert the extraction rod
in the hole located in the lower
part of the circuit breaker.
22
ABW - Air Circuit Breaker
rails.
2. Position the circuit
breaker on the rails,
paying attention to the
perfect fitting.
CAutIon!
The extraction rod can only be inserted
with the "OFF" button pressed.
The position lock comes out whenever
the operation is concluded. Then go on
to the next step.
3. Slowly push the
circuit breaker inside the
extraction car.

Publicidad

Tabla de contenido
loading

Tabla de contenido