Installation
Control Function Test
The machine should be cleaned after the installation is
complete. A function test should then be executed on
the unloaded machine:
1. Check the power supply for correct voltage,
phase, and cycles to be sure they are correct for
the machine.
2. Open manual shut-off valves to the machine.
3. Turn on electric power.
4. Check the lid interlock before starting operation:
a. Open the lid to the extract-rinse compartment.
b. Attempt to start the machine with the lid open.
The machine should not start with the lid
open.
c. Close the lid without locking it and attempt to
start the machine. The machine should not
start with the lid unlocked.
d. Close and lock the lid and start a cycle.
Attempt to open the lid while the cycle is in
progress. The lid should not open.
If the lid lock and interlock are not functioning
properly, call a service technician.
5. Run a complete cycle, checking operation of
water inlet valves, drain, and extract functions.
6. Check that cylinder rotation is clockwise in the
extract step. If rotation is not clockwise in the
extract step, disconnect power and have a
qualified electrician reverse lines L1 and L2 at
the J-box.
16
F232113