NEMA MONUMENT INSTALLATION
7.
At this point, DO NOT remove the protective cover from the
NEMA Monument (7a). Determine the desired orientation of the
NEMA Monument (7b). The NEMA filler determines the orientation
of the NEMA Monument. Install the NEMA filler with two (2) M4
screws with a T20 torx bit to 7-10 in-lbs torque (7c).
7b
NOTE: The NEMA Monument is not installed at this point.
NOTE: Remove protective cover after flooring has been installed.
PARALLEL ORIENTATION
NEMA FILLER
REMOVE PROTECTIVE COVER AFTER
FLOORING HAS BEEN INSTALLED
7c
PERPENDICULAR ORIENTATIONS

NEMA MONUMENT

PROTECTIVE COVER
7a
PARALLEL ORIENTATION SHOWN
Page 15 of 75
24207101 Rev G