Activate Loads in Bypass

Activate Loads in Bypass
A. Complete load wiring.
B. Check that the bypass jumpers are in place.
These jumpers protect from load faults and must
be used to check load wiring when it is installed
or modified.
Caution! Verify that the panel is fed from the
correct voltage. A feed miswire or loss of a
feed neutral can cause damage to the
equipment.
C. Turn circuit breaker 1 ON.
The load(s) should energize, the breaker should
not trip, and total load current must be within
the circuit breaker's limit and less than or
equivalent to 16 A.
Circuit breaker 1 powers the control wiring as
well as Circuit 1's dimmer and load(s). Check
that the Power OK LED on the Controller
(LCP128) or circuit selector (LP or CCP) is ON. If
the Power OK LED is OFF, turn OFF the control
circuit breaker (breaker 1) and check for a
miswire on the low voltage link.
D. Turn next circuit breaker ON.
The load should energize, the breaker should
not trip, and total load current must be within
the circuit breaker's limit and less than or equal
to 16 A.
E. Repeat step D for each circuit with
completed load wiring.
16
Installation Guide for Dimming and Switching Panels
Load circuit wiring
AC RMS current
DH
DH
DH
DH
H
H
N
N
Bypass
N
N
jumper
N
LCP-8D-1204ML-20 shown
'Power OK' LED
at the bottom of LCP128
Controller
'Power OK' LED
1
at the top of LP/CCP Circuit
Selector
2
N
LP3/12-1204ML-20 shown
R