Installation instruction
B. Leakage test
1. The outdoor unit has been executed the leakage test in the factory. After connecting the distributing pipe, execute the
leakage test from the outdoor check valve and the indoor. Besides, while testing, the valves should be close.
2. Refer to the below figure to charge the nitrogen into the unit to take a test. Never use the chlorin, oxygen, flammable
gas in the leakage test. Apply pressure both on the gas pipe and the liquid pipe.
3. Apply the pressure step by step to the target pressure.
a. Apply the pressure to 0.5MPa for more than 5 minutes, confirm if pressure goes down.
b. Apply the pressure to 1.5MPa for more than 5 minutes, confirm if pressure goes down.
c. Apply the pressure to the target pressure (4.0MPa), record the temp. and the pressure.
d. Leave it at 4.0MPa for over 1 day, if pressure does not go down, the test is passed. Meanwhile, when the temp.
changes for 1degree, pressure will change 0.01MPa as well. Correct the pressure.
e. After confirmation of a~d, if pressure goes down, there is leakage. Check the brazing position, flared position by
laying on the soap. modify the leakage point and take another leakage test.
4. After leakage test, must execute the evacuation.
Nitrogen
C. Evacuation
Evacute at the check valve of liquid stop valve and both sides of the gas stop valve.
Operation procedure:
Because the unit is with refrigerant R410A, the below issues should be paid attention:
• To prevent the different oil into the pipe, please use the special tool for R410A, especially for gauge manifold and
charging hose.
• To prevent the compressor oil into the refrigerant cycle, please use the anti-counter-flow adapter.
D. Check valve operation
Open/close method:
• Take down the valve cap.
• Turn the liquid stop valve and the gas stop valve with hexangular spanner until it stops. If opening the valve strongly,
the valve will be damaged.
• Tighten the valve cap.
Lo handle
After reaching -101KPa or
less (below -755mmHg), let
the vacuum pump running
continuously for over 1hour.
If vacuum pointer arises, it shows there is water or leakage in the
system, please check and modify it, and then evacuate again.
To indoor
Gauge manifold
Lo
Hi
Hi handle
Leave it for over 1
hour, vacuum pointer
does not arise.
12
Check valve
Gas pipe
Gas pipe
Check hole
Outdoor