5 LCS-Tool
Make sure that all inverters are present. It is possible to
continue the configuration of the listed inverters even if not
all inverters are detected. The undetected inverters can
always be configured later.
8. Select the desired country from the list of options
available for the inverters in the network (see figure
13).
Figure 13: LCS-Tool - selecting the country and grid code
10. The LCS tool prompts for a confirmation of the selected
country and grid code. In case of battery storage
systems, the battery details are additionally shown. A
wrong configuration can be changed by clicking the
[Back] button and by changing the settings in the
previous window.
11. The system then applies the grid code selected on the
Inverter Manager to the detected inverters. Any
inverter added at a later stage automatically inherits
the same grid code. The application of only one grid
code is possible per Inverter Manager.
16
IMVIOBOX-IA-xx-17
9. Select the desired grid code from the list of options
available for the selected country. If necessary, load a
customer specific grid code by clicking the button
[Load] (see figure 13). The button [Create] is inactive
and cannot be used.
INFORMATION
It is essential to choose the correct grid code. A
modification after the first ten operating hours have
passed is only possible with a personal SMA Grid
Guard code.
The grid code parameters can be changed
subsequently with the LCS-Tool (see Section 5.2.9,
page 26). Prerequisite is the use of the latest version
of the LCS-Tool.
12. A green square identifies the commissioned inverters.
The inverters are only connected to the utility grid when
the [Start] command has been carried out from the bar
below the start menu (see figure 14).
SMA Solar Technology AG
Installation manual