Carefully check the characteristics and consistency of the wall in
order to possibly choose wall plugs specific for particular situa-
tions.
The manufacturer will not be held liable for any underestimates
made in the structural consistency of the anchor prepared by the
installer. Therefore, pay utmost attention to the foregoing opera-
tion that could cause serious injury/damage to people/property if
carried out incorrectly.
When installing models equipped with heating pump, if no condensate discharge
was built into the wall (see paragraph 2.4.2), in order to drain the condensate
it will be necessary to drill a hole through the wall in the position shown on the
template.

2.4.2 - Preparing the condensate discharge

As regards machines with heat pump, a
condensation drain pipe (fig. 1 - ref. N)
(supplied) to be inserted in the specific
connection (A) (fig. 7).
Remove the cap (B) (fig. 7) before
inserting the condensation drain pipe .
When the max level is reached, a so-
lenoid valve ensures the condensate
will flow out from the internal tray.
For cold-only machines, connect the
condensate discharge pipe if you
intend running the unit at low outdoor
temperatures (lower than 23°C).
Since condensate drains by gravity,
there must be a minimum slope of at
least 3% at every point of the discharge
line. Use a rigid or flexible tube having
an inside diameter of at least 16 mm.
If the line empties into a sewerage system, install a siphon before the point in
which the pipe reaches the main discharge, at least 300 mm below the inlet from
the unit (fig. 8).
EN - 16
7
A
B
8
min
300
mm